What about inspections?

It is the responsibility of the permit holder or contractor to call us for inspections at specific times during construction.  Please remember that inspections require a 24-hour notice.  Inspections are made during certain points in the project, depending on the type of project.  For example, retaining walls require inspections of the footing, after block is laid and steel placed but before grouting, after back fill has been placed, and when the project is complete.

Remember . . . the project is not legally complete until it has passed the final inspection.

 

 